+91 99726 08515info@talwin.inMon–Sat 9:30 AM – 7:00 PM
BTM 4th Stage, BengaluruFollow usBecome a Dealer →
Solar

BESCOM Net Metering Process 2026: Steps, Documents, Timeline & Status Check

Net metering lets you export surplus solar power to BESCOM and get credit on your bill. Here's exactly how the process works in Bangalore.

19 Sep 2026 · 3 min read · By Talwin Solar & Water Experts
BESCOM Net Metering Process 2026: Steps, Documents, Timeline & Status Check

Net metering allows your rooftop solar system to export surplus electricity to the BESCOM grid. A bi-directional meter records both import and export, and you're billed only for the net units.

Step-by-step process

  1. Application through the PM Surya Ghar national portal (for residential subsidy) or BESCOM's rooftop solar process, with your RR/consumer number.
  2. Technical feasibility — BESCOM checks transformer capacity and approves the system size.
  3. Installation by your vendor using approved panels and inverter.
  4. Work completion report and documents submitted.
  5. Inspection & bi-directional meter installation by BESCOM.
  6. Commissioning — your system goes live; subsidy (if applicable) is processed.

Documents typically required

  • Latest electricity bill
  • ID proof and property ownership proof
  • Site photos and system details
  • Vendor installation & test reports
  • Bank details (for subsidy)

How long does it take?

Typically 2–6 weeks from application to commissioning, depending on documentation, sub-division workload and meter availability.

Talwin handles your complete BESCOM net-metering paperwork.

Get Free Quote

Checking your application status

You can track progress on the portal where you applied using your application or consumer number. Your vendor can also follow up with the local BESCOM sub-division.

Tips for a smooth approval

  • Keep the connection name and property documents consistent.
  • Don't oversize beyond your sanctioned load without applying for enhancement.
  • Use ALMM/DCR panels if you want the subsidy.

Frequently Asked Questions

Do I get paid for exported units?

Exported units are credited against your consumption as per prevailing KERC/BESCOM regulations.

Is net metering available for commercial buildings?

Yes, commercial and industrial consumers can also apply, subject to applicable regulations.

Need expert advice for your home or business? Free site visit across Bengaluru.

Get Free Quote

Disclaimer: prices, tariffs and subsidy figures are indicative and based on publicly available information at the time of writing; they can change. Contact us for current, site-specific figures.

Liked this guide? Follow us on LinkedIn

We share new solar & water guides, subsidy news and project stories every week.

  • ☀ Subsidy & BESCOM updates
  • 💧 Water & energy saving tips
  • 🏗 Real project showcases
  • 🤝 Dealer & career openings
Follow on LinkedIn
Chat on WhatsApp +91 99726 08515
CallWhatsApp